The builder agreed it by email. Then the contract got signed.
$162,000 for a warranty that turned up late
WA’s new trust law for subbie money
|
|
|
This week starts something new in the Toolbox. My contract review checklist has the 11 pitfalls I see most in builders’ contracts. I’m pulling them out one at a time, and Pitfall 6 is first, because it’s this week’s story.
Straight in.
|
|
|
|
Doing the Rounds
WA · Security of payment · Royal Assent 21 October 2026
WA has passed trust accounts for subbie money on government jobs. They’re not switched on yet.
|
|
What’s coming in WA
| Which jobs | WA State Government jobs over a threshold, expected to be $1.5 million including GST. |
| The money | Held in a trust account, with retention in a separate one. |
| Your share | What’s certified, scheduled or agreed in writing. |
| When | No start date yet. It starts when the government proclaims it. |
|
| GET YOUR NUMBERS AGREED IN WRITING. |
|
| Building and Construction Industry (Security of Payment) Amendment Act 2026 (WA) |
|
| • | WA’s Parliament passed the Building and Construction Industry (Security of Payment) Amendment Act 2026. It got Royal Assent on 21 October. |
| • | On WA State Government jobs over the threshold, the money paid to the head contractor goes into a trust account, ring-fenced from the head contractor’s creditors if it goes under. Retention goes into a separate trust account. |
| • | Head contractors will have to tell the government, with each claim, whether their subbies have been paid, and if not, how much is owed and why. |
| • | None of it has started. Apart from the opening section, the whole Act starts on dates the government hasn’t set yet. |
|
What it means for you
If you work on WA government jobs, this is good news, once it starts. Money owed to you gets held in trust instead of sitting in the builder’s bank account.
But look at what the trust covers: amounts certified, scheduled or agreed in writing. A verbal yes on site doesn’t get you a share of the trust. Same lesson as Off My Desk this week.
Not in WA? Queensland has had trust accounts on bigger jobs for a few years now, and the idea keeps spreading. Either way, the habit’s the same: get your numbers in writing.
Western Australia, State Government jobs only. Not in force yet. General information, not advice on your job.
|
|
|
|
The Number
$162,000
Liquidated damages claimed against a roofer who’d finished on site, but hadn’t handed over a warranty.
|
|
|
A roofing and cladding subbie on a Queensland school job. The date for completion was 1 November 2020. The work on site was done by about the middle of December.
The last warranty, from the steel supplier, didn’t turn up until August 2021.
The subcontract said completion needed every warranty and certificate handed over. So the builder said completion hadn’t happened, and claimed liquidated damages at $1,000 a day. By the time it sued, that was $162,000.
The roofer argued the clause was uncertain, that it was a penalty, and that the builder’s own delays knocked it out. The District Court said no to all three. Those were questions decided ahead of trial, so the final bill wasn’t settled there.
The lesson: read what completion means in your contract. If it says warranties, start chasing them the day you start the job, not the day you finish. That’s Pitfall 4 in the series, and it’s coming.
Midson Construction (Qld) Pty Ltd v The Haggarty Group Pty Ltd [2021] QDC 280.
|
|
|
|
Off My Desk
It was in writing. It still might not count.
|
|
Where a promise needs to live
| An email before you sign | Can be wiped out by the entire agreement clause. |
| Before you sign | Write it into the contract: the scope, the special conditions or the rates. |
| After you sign | Get it as a written variation, before you do the work. |
| “He said he’d sort it” | Isn’t in the contract. |
|
| IF IT’S NOT IN THE CONTRACT, IT MIGHT NOT BE IN THE DEAL. |
|
|
|
A concreter in south-east Queensland was close to signing a subcontract on a commercial job. Weeks of back and forth, and nearly everything was agreed.
One last question: who pays for a vac truck to clean up the wash-off from the exposed aggregate? He held his ground, and the builder’s contracts manager confirmed by email that the builder would pay.
Job done? Not quite. The contract had a clause in it that just about every builder’s contract has. In plain English, it says:
|
|
The signed contract replaces any earlier understanding.
|
|
|
That’s the entire agreement clause. Once both sides sign, the contract is the whole deal. Anything agreed before that, in an email, on the phone or at the pre-start, can fall away unless it’s written into the contract itself.
What we did. Told him the email might not survive signing. In his reply to the builder we added one line: once it’s signed, please issue the vac truck as a written variation under the variations clause, so it’s recorded against the contract. Before the truck turns up.
What it teaches. An email shows what was said. The contract is what was agreed. Get the two to match.
Watch for. The last few points settled in a hurry because the builder wants it signed today. That’s when promises end up in emails instead of the contract.
Queensland. Live matter, no outcome yet. General information only.
Details changed. The lesson isn’t.
|
|
|
|
Two-Minute Fix
Find the promises that aren’t in your contract.
Pick your biggest job. Two minutes in your inbox.
| 1. | Search your email for the builder’s name, back to before you signed. Look for “we’ll cover”, “no problem”, “agreed” and “confirmed”. |
| 2. | For each promise, check the signed contract. Is it in the scope, the special conditions or the rates? |
| 3. | If it isn’t, and the work’s still coming, email the builder now and ask for it as a written variation before you do it. |
| 4. | If it’s already done, raise it with the builder in writing now. Not at final account. |
And the Christmas cliff: NSW is this Thursday, 26 November, on the longest terms. On or after your date. Never before.
|
|
|
|
|
The Toolbox
Pitfall 6 of 11: the entire agreement clause, free
One page, straight out of my contract review checklist. The clause that can wipe out your quote, your emails and anything agreed at the pre-start, and what to do about it before you sign.
Over the coming months I’ll pull out the other ten, one at a time.
|
|
|
|
Free PDF, no sign-up. It’s general information. Your own contract decides what’s in and what’s out.
|
|
|
|
The Academy Bit · this is the ad
Plenty of delay notice templates finish with a line like this: “This estimate is preliminary and is not an extension of time claim.”
Cut it. If your EOT claim ever misses its deadline, that’s the sentence the builder quotes back at you. Say instead that the notice doesn’t limit any claim for an extension of time, which will follow.
What you write counts too. The Tradies Academy toolkit is built for exactly this.
It reads your own contract, finds the notice clauses and their deadlines, and drafts the Notice of Delay and the EOT claim from that same contract. It never sends anything. You check it and press Send. And the first notice on each job comes to me for a free check.
Foundation places are still going: the toolkit and the whole Academy for $127 a week, locked in for as long as you stay. After that, the toolkit sits in its own tier at $197 a week.
It runs inside Claude on your own computer, so you’ll need your own paid Claude plan (Pro or above). I set it up with you.
Foundation places are hand-picked, so we’ll have a chat first. Not ready? Fair enough. Smoko’s still free every Tuesday.
|
|
|
That's the week.
Has a builder ever gone back on something they agreed before you signed? Hit reply and tell me how it played out.
See you next smoko.
- Jason
|
Construction Claims and Disputes. Nearly 40 years in construction.
This is the web copy of Smoko, the weekly email from Construction Claims and Disputes. Get it in your inbox. General information only, not legal advice. PO Box 918, Paddington QLD 4064
|
|
Get the next one in your inbox.
Smoko lands every Tuesday morning. Free. Unsubscribe any time.
Join Smoko free
|